Pacific Beach 136-Unit ADU Foreclosure: Developer Battle 2026
A legally permitted 136-unit ADU development in Pacific Beach faces foreclosure auction, ongoing litigation, and a December 2025 court-ordered construction halt that exposes the critical gap between legal rights and practical project feasibility.
A legally permitted 136-unit ADU development in Pacific Beach has become a cautionary tale for builders across San Diego's coastal communities. The Chalcifica project on Pacifica Drive and Chalcedony Avenue—despite having all required permits under California's aggressive ADU expansion laws—faces foreclosure auction, ongoing litigation, and a December 2025 court-ordered construction halt that exposes the critical gap between legal rights and practical project feasibility.
For builders considering multi-unit ADU projects in Pacific Beach, La Jolla, Mission Beach, or Bird Rock, this case demonstrates that even bulletproof legal compliance cannot guarantee project success when community opposition, environmental concerns, and financial vulnerabilities converge. La Jolla builders face similar CEQA challenges when developing near coastal bluffs and known Kumeyaay archaeological sites. Mission Beach's higher existing density creates different dynamics—smaller ADU projects blend more naturally with the area's established multi-family character. Bird Rock's premium property values, exceeding $3 million for detached homes, make ADU investment attractive despite the 20-30% coastal construction premium that affects all San Diego beach communities. The foreclosure battle offers essential lessons on risk management, community engagement, and the realities of mega-scale ADU development in established coastal neighborhoods.
The Chalcifica Project: Ambition Meets Reality
The Chalcifica development represents one of the largest ADU projects attempted in Pacific Beach. Planned for three consolidated parcels on Pacifica Drive and Chalcedony Avenue in the 92109 zip code area of North Pacific Beach, approximately eight blocks from the Pacific Ocean, the project would create six three-story buildings containing 136 one-bedroom units with only 70 parking spaces—a density that dramatically exceeds the surrounding single-family neighborhood character.
Original developer SDRE Homebuyers obtained permits in June 2023 under California's ADU expansion laws, which allow property owners to build multiple units on consolidated parcels without traditional discretionary review. The project appeared legally sound: state law permitted the density, local ordinances had been updated to comply with AB 434 and AB 976, and the city initially treated it as a ministerial approval requiring no environmental review.
But legal permission didn't translate to community acceptance. In August 2025, the group "Neighbors for a Better Pacific Beach" filed suit against the City of San Diego and SDRE, arguing the project posed environmental risks and sat on the historically significant Kumeyaay archaeological site known as La Rinconada de Jamo (CA-SDI-5017). Residents objected to the project's size, raising concerns about traffic congestion, fire hazards, infrastructure strain, and impacts to culturally significant Kumeyaay lands.
December 2025 Court Order Halts Construction
The litigation achieved rapid results. In December 2025—just four months after the lawsuit was filed—a California Superior Court judge issued a preliminary injunction halting all construction activity. The court ruling required full environmental review under the California Environmental Quality Act (CEQA) due to potential impacts on La Rinconada de Jamo, a Kumeyaay coastal village site with over 2,500 years of documented occupation.
The archaeological significance proved decisive. La Rinconada de Jamo, located at the mouth of Rose Canyon where its drainage empties into Mission Bay, represents one of the earliest documented European-Indigenous contact sites in California—the first Spanish expedition encountered a large Kumeyaay settlement here on July 14, 1769. Excavations have found evidence of shellfish processing, marine mammal harvesting, and fish consumption spanning millennia, with occupation continuing into the 1890s.
The city's attempt to bypass environmental review through ministerial approval—essentially rubber-stamping the project without public oversight or CEQA analysis—became the legal vulnerability that stopped construction. The judge determined that impacts to such a significant archaeological resource required discretionary review and full environmental analysis, not the streamlined approval process the city had applied.
May 2026 Foreclosure Notice and Developer Transition
The construction halt triggered a financial crisis. By May 2026, Pacific Beach residents discovered public notices posted near the Pacifica Drive parcels indicating the property was in default and scheduled for foreclosure auction on May 28, 2026 unless developer SDRE satisfied the amounts owed.
In April 2026—just weeks before the foreclosure auction—a corporate restructuring complicated the situation further. Infill Innovation, a newly formed development company, acquired SDRE Homebuyers. Christian Spicer, SDRE's founder often dubbed the "King of San Diego's Mega-ADU Projects," stepped down as CEO, with Brian Doyle assuming the role of President and Chief Business Officer at Infill Innovation.
Doyle immediately disputed the foreclosure proceedings, stating "The foreclosure is without merit" and asserting that Infill Innovation is working with Pacific Beach residents on an "amicable resolution" to end the lawsuit. As of July 2026, the project remains stalled with no construction activity, though legal negotiations continue.
Infill Innovation's portfolio includes 84 projects totaling approximately 1,400 apartments across San Diego, with about 25% completed by mid-2026 and the balance due for completion in 2027-2028. The company's ability to resolve the Chalcifica dispute while managing this broader portfolio will be closely watched by industry observers.
The Legal Framework: Why 136 Units Were Permitted
Understanding how a 136-unit mega-project received approval in a single-family neighborhood requires examining California's ADU regulatory evolution. Multiple state laws created the framework that made Chalcifica legally possible:
AB 976 (Effective January 1, 2026): This legislation permanently eliminated owner-occupancy requirements for ADUs, allowing developers to build rental units without living on-site. Previously, AB 881 provided temporary owner-occupancy relief through 2025; AB 976 made this permanent, opening the door for large-scale investor-driven ADU projects. Learn more about AB 976's impact on Pacific Beach ADU investment.
AB 434 (January 2026): Required all California cities to offer pre-approved ADU plans posted online, streamlining the approval process to as little as 30 days for projects using standard designs. This dramatically reduced approval timelines and removed discretionary review for conforming projects. Read about AB 434's pre-approved ADU plans.
San Diego Bonus ADU Program: San Diego's local implementation proved remarkably permissive. For single-family properties, the program allows up to 4 units on lots under 8,000 square feet, 5 units on lots between 8,001-10,000 square feet, and 6 units on lots exceeding 10,000 square feet. The program has been described as "perhaps more permissive than any small lot redevelopment zoning reform anywhere in the United States."
Lot Consolidation Strategy: By consolidating three adjacent parcels on Pacifica Drive and Chalcedony, SDRE created a larger development site that maximized allowable ADU count under San Diego's bonus program. This legal strategy—combining multiple lots to multiply unit allowances—has become common among large-scale ADU developers.
The result: a project with 136 units, six three-story buildings, and only 70 parking spaces was technically compliant with all applicable laws. But compliance with ADU statutes didn't address CEQA obligations for environmental review, particularly when significant archaeological resources were present.
Financial Vulnerabilities of Stalled Mega-Projects
The Chalcifica foreclosure illustrates how litigation-induced construction delays create financial death spirals for large-scale ADU developments. Several cost factors compound when projects stall:
Carrying Costs Without Revenue: Land acquisition debt, property taxes, and construction financing continue accruing interest during litigation delays, with no rental income to offset expenses. For a 136-unit project in Pacific Beach, monthly carrying costs could easily exceed $50,000-$75,000 even with construction halted.
Construction Cost Inflation: San Diego construction costs increased 3.5% in 2026 according to Turner & Townsend forecasts, but labor costs are rising 6-8% annually with 92% of firms reporting hiring challenges causing project delays. Each month of delay makes the original budget obsolete, requiring additional capital to complete construction. Understand the broader context of San Diego construction costs and tariff impacts.
Legal Defense Expenses: CEQA litigation in California typically costs $150,000-$500,000+ to defend, depending on complexity and duration. For a project facing environmental review requirements, archaeological surveys, tribal consultations, and ongoing negotiations, legal costs can quickly exceed $250,000.
Coastal Construction Premium: Projects in Pacific Beach, La Jolla, Mission Beach, and Bird Rock all face 20-30% higher construction costs compared to national averages due to coastal location and Coastal Development Permit requirements. ADU construction in San Diego typically costs $375-$600 per square foot for turnkey detached units, with coastal areas at the higher end. A 136-unit project could represent $40-60 million in total development cost—making foreclosure exposure extremely high. See detailed information on coastal ADU construction costs in Pacific Beach.
Opportunity Cost: Developer capital and staff time locked into a stalled project cannot be deployed to other opportunities. For companies like Infill Innovation managing 84 projects totaling 1,400 units, having a significant project frozen creates portfolio-wide liquidity challenges.
Community Opposition Dynamics in Established Neighborhoods
The intensity of Pacific Beach community resistance reveals critical lessons about neighborhood acceptance thresholds. Even legally permitted projects face litigation risk when several factors converge:
Scale Mismatch: Placing six three-story buildings with 136 units in an established single-family neighborhood creates dramatic visual and density contrast. The project would have fundamentally altered the residential character of Pacifica Drive and Chalcedony Avenue, transforming quiet residential blocks into a multi-family apartment complex.
Infrastructure Concerns: Residents raised legitimate questions about traffic (particularly along Chalcedony Avenue's residential access to Garnet Avenue commercial corridor), parking (only 70 spaces for 136 units), emergency vehicle access, and fire safety. While ADU laws streamline approval, they don't require infrastructure capacity analysis—creating a disconnect between legal permission and practical feasibility.
Cultural Resource Protection: The location on La Rinconada de Jamo proved particularly sensitive. This wasn't abstract environmental concern—the site represents 2,500+ years of Kumeyaay occupation and marks the first documented Spanish-Indigenous contact in Alta California (July 14, 1769). Archaeological research documents shellfish processing, marine mammal harvesting, and continuous village occupation into the 1890s.
Organized Opposition: Neighbors for a Better Pacific Beach demonstrates effective community organizing. The group's lawsuit achieved a preliminary injunction within four months—remarkably fast in CEQA litigation. Their strategy targeted a genuine legal vulnerability (lack of environmental review) rather than simply opposing density, making their case legally sustainable.
Proximity to Kate Sessions Park: The project's location near Kate Sessions Memorial Park and north of Garnet Avenue, Pacific Beach's main commercial corridor,—a beloved 79-acre hilltop park offering panoramic views of Mission Bay, downtown, and the Pacific Ocean—heightened community sensitivity. The park area represents North Pacific Beach's quieter, more upscale residential character where detached properties regularly exceed $2 million.
Risk Management Lessons for Coastal Builders
The Chalcifica foreclosure battle offers actionable guidance for builders evaluating ADU construction in Pacific Beach, La Jolla ADU development, Mission Beach coastal building projects, and Bird Rock residential construction:
1. Right-Size Projects to Neighborhood Context: Legal permission to build 136 units doesn't mean you should. Projects that respect existing neighborhood scale—perhaps 8-12 units instead of 136—face dramatically lower litigation risk. Smaller projects can still generate strong returns while avoiding the community opposition that triggers costly legal battles.
2. Conduct Environmental Due Diligence Early: Don't rely on ministerial approval processes to avoid CEQA review. Proactively commission Phase I archaeological surveys, especially in coastal areas with known Indigenous occupation history. The $5,000-$15,000 cost of early environmental assessment is trivial compared to the cost of litigation-induced construction halts.
3. Structure Financing with Litigation Reserves: Budget for 12-18 month litigation delays when evaluating large-scale ADU projects. Construction financing should include reserves for legal defense ($250,000+), carrying costs during stalls, and cost inflation. Most lenders require 15-20% equity remaining in your primary property after ADU financing, but mega-projects need significantly deeper capital reserves.
4. Engage Community Before Permit Submission: Proactive neighborhood meetings, design charrettes, and genuine response to concerns can identify fatal flaws before investing in permits and design. While not required for ministerial ADU approvals, community engagement reduces litigation probability—a much better investment than legal defense costs.
5. Understand CEQA Exemption Limits: ADU ministerial approval doesn't automatically exempt projects from CEQA when significant environmental impacts exist. Archaeological resources, tribal cultural resources, biological habitat, and coastal resources can all trigger discretionary review requirements regardless of ADU law streamlining.
6. Evaluate Tribal Consultation Requirements: San Diego's CEQA process includes government-to-government consultation with Kumeyaay tribes to protect tribal cultural resources. Projects in areas with known Indigenous occupation should engage tribes early, not after litigation forces the issue.
7. Monitor Regulatory Shifts: San Diego added lot-size caps to its ADU Bonus Program in 2026, demonstrating that politically vulnerable programs can change. Projects exploiting maximum allowances may face regulatory backlash mid-development. Sustainable ADU investment should be based on stable, long-term frameworks rather than maximum legal exploitation.
Alternative Approaches: Successful ADU Development in Pacific Beach
Not all Pacific Beach ADU projects face litigation. Successful developments share common characteristics that avoided the pitfalls that trapped Chalcifica:
Smaller Scale: Projects with 4-8 units rather than 136 units blend better with neighborhood character. Individual ADU conversions and small multi-unit developments continue proceeding smoothly through Pacific Beach permitting with minimal opposition.
Regional Variations: Each coastal service area presents distinct ADU opportunities. La Jolla's established single-family neighborhoods and stringent architectural review create higher design costs but also support premium rental rates ($3,000-$4,500+ monthly for one-bedroom ADUs near UCSD). Mission Beach's existing multi-family zoning and beach-proximity rentals make 4-8 unit ADU projects more compatible with neighborhood character than in purely residential Pacific Beach blocks. Bird Rock's compact geography and walkability to restaurants and shops create strong ADU tenant demand despite limited parking. Tourmaline Surfing Park area attracts surf-focused renters willing to pay premium rates for beach access.
Appropriate Design: ADUs designed to match existing architectural character—craftsman bungalows, Spanish colonial, California coastal styles—generate far less resistance than generic three-story apartment blocks. Design guidelines and architectural finesse ensure ADUs become organic extensions of existing neighborhoods rather than jarring contrasts.
Adequate Parking: While ADU laws eliminate minimum parking requirements, providing reasonable parking (0.5-1 space per unit) addresses neighbor concerns and demonstrates good-faith community consideration. The Chalcifica ratio of 70 spaces for 136 units (0.51 spaces/unit) technically complied with law but amplified opposition.
Transparent Communication: Developers who meet with neighbors, explain projects honestly, and make reasonable design adjustments based on feedback build goodwill that prevents litigation. Community engagement isn't legally required for ministerial ADUs, but it's a practical necessity for large-scale projects.
Phased Development: Building in phases—starting with one parcel before consolidating and expanding—allows developers to test neighborhood response, refine designs, and build trust before committing full capital to mega-scale projects. It also reduces financial exposure if unexpected opposition emerges.
The Future of Mega-ADU Projects in San Diego
The Chalcifica case may represent a turning point for California's ADU expansion strategy. While state laws created legal pathways for 136-unit projects, the practical reality of community opposition, CEQA requirements, and financing vulnerabilities suggests these mega-projects face systemic challenges beyond individual developer execution.
Several trends suggest mega-ADU projects will face increasing scrutiny:
Regulatory Corrections: San Diego's 2026 addition of lot-size caps to its Bonus ADU Program signals recognition that unlimited density allowances created politically unsustainable outcomes. Other California cities are likely to follow with similar constraints that maintain ADU opportunities while preventing neighborhood-scale transformations.
Enhanced Tribal Consultation: The Chalcifica case demonstrates that archaeological and tribal cultural resources remain robust legal backstops against inappropriate development, even in the ministerial ADU approval context. Expect developers to face more stringent tribal consultation requirements going forward.
Community Organization: Neighbors for a Better Pacific Beach provides a successful litigation model that other neighborhoods will replicate. The rapid achievement of a preliminary injunction (four months) shows that well-organized community groups with legitimate legal claims can effectively deploy CEQA to halt projects.
Financing Caution: Lenders observing the Chalcifica foreclosure will likely impose stricter underwriting standards for mega-ADU projects, requiring deeper capital reserves, lower loan-to-value ratios, and community acceptance assessments before funding. This will naturally constrain project scale.
Developer Adaptation: Infill Innovation's stated pursuit of an "amicable resolution" with Pacific Beach residents suggests sophisticated developers are recognizing that litigation fights—even when legally defensible—destroy project economics. Expect future mega-projects to include upfront community engagement and scale moderation.
Regional ADU Development Dynamics Across San Diego's Coastal Communities
While the Chalcifica case unfolded in Pacific Beach, the lessons extend across all San Diego coastal service areas, each with distinct development dynamics:
La Jolla ADU Construction: La Jolla's established single-family neighborhoods present similar community acceptance challenges as North Pacific Beach, but with even higher architectural review standards. Projects near UCSD benefit from consistent graduate student and faculty rental demand, supporting $3,000-$4,500+ monthly rates for well-designed one-bedroom ADUs. However, La Jolla builders must navigate stricter Coastal Development Permit requirements and heightened sensitivity to archaeological resources—the same CEQA vulnerabilities that halted Chalcifica apply with equal force to La Jolla coastal sites.
Mission Beach Multi-Unit Development: Mission Beach's existing multi-family zoning and beach-centric character create different ADU dynamics than Pacific Beach. Smaller 4-8 unit projects blend more naturally with Mission Beach's established density, facing less community opposition than in single-family zones. However, Mission Beach's constrained geography between Mission Bay and the Pacific Ocean creates infrastructure challenges—parking, traffic, and emergency access concerns similar to those raised against Chalcifica apply with even greater intensity in Mission Beach's narrow beach community layout.
Bird Rock Coastal Construction: Bird Rock's compact, walkable neighborhood and premium property values ($3+ million for detached homes) make ADU investment economically attractive despite coastal construction premiums. Bird Rock's established community character and active neighborhood association suggest smaller-scale ADU projects (1-2 units) face smoother approval than mega-projects. The same principle demonstrated by Chalcifica—legal permission doesn't guarantee community acceptance—applies throughout Bird Rock's tight-knit residential blocks.
Tourmaline Surfing Park Area: The Tourmaline area's proximity to Pacific Beach's premier surf break creates unique rental dynamics. Surf-focused tenants pay premium rates for beach access, but projects must respect the area's low-scale residential character and parking constraints near the beach. Environmental review requirements for coastal bluff stability and beach access apply throughout the Tourmaline area, creating similar CEQA exposure as the Chalcifica project's archaeological sensitivity.
Conclusion: Balancing Housing Production with Community Acceptance
The Pacific Beach 136-unit ADU foreclosure battle crystallizes California's fundamental housing policy tension: how to dramatically increase residential density to address the housing crisis while respecting established neighborhood character and environmental protection requirements.
For builders and developers planning Pacific Beach ADU projects, La Jolla coastal construction, Mission Beach development, and Bird Rock residential building, the Chalcifica case offers clear guidance: legal permission is necessary but insufficient for project success. Sustainable ADU development requires balancing state law opportunities with community context, environmental due diligence, robust financing, and realistic assessment of neighborhood acceptance thresholds.
Projects scaled appropriately to their surroundings, designed with architectural sensitivity, and developed with genuine community engagement will continue succeeding in Pacific Beach's strong rental market. But mega-scale projects attempting to maximize every legal allowance without considering practical constraints face the litigation, community opposition, and financial vulnerabilities that have trapped Chalcifica in a foreclosure battle that may ultimately kill the project entirely.
The gap between what California law permits and what Pacific Beach neighborhoods will accept remains wide. Builders who navigate this gap thoughtfully—prioritizing long-term project success over maximum unit count—will capture the substantial ADU opportunity in San Diego's coastal communities. Those who push legal boundaries without environmental and community diligence risk following Chalcifica's path: legally compliant but practically failed, with foreclosure notices posted on properties that may never be developed as originally envisioned.
Considering a multi-unit ADU project in Pacific Beach or surrounding coastal areas? Pacific Beach Builder provides comprehensive feasibility assessments that evaluate not just legal compliance, but community context, environmental requirements, and financial risk factors. Our 15+ years of Pacific Beach experience helps clients distinguish viable opportunities from projects likely to trigger the opposition and litigation that have stalled the Chalcifica development. Contact us for a consultation that addresses the full spectrum of ADU development risks—before you invest in permits and design.
Frequently Asked Questions About the Chalcifica ADU Foreclosure
What is the current status of the Pacific Beach 136-unit Chalcifica ADU project?
As of July 2026, the Chalcifica project remains halted under a December 2025 court order requiring full environmental review under CEQA. A May 28, 2026 foreclosure auction was scheduled when public default notices were posted, but new owner Infill Innovation (which acquired original developer SDRE in April 2026) disputes the foreclosure as "without merit" and is reportedly working on an "amicable resolution" with Neighbors for a Better Pacific Beach. No construction activity is currently occurring, and the project's future remains uncertain pending litigation resolution.
Why was a 136-unit ADU project permitted in a single-family neighborhood?
California's aggressive ADU expansion laws (AB 976, AB 434) combined with San Diego's remarkably permissive Bonus ADU Program created the legal framework. By consolidating three adjacent parcels on Pacifica Drive and Chalcedony Avenue, SDRE maximized allowable unit counts under San Diego's program, which permits up to 6 units on lots exceeding 10,000 square feet. The city initially treated it as ministerial approval requiring no environmental review. However, the court later ruled that impacts to the La Rinconada de Jamo Kumeyaay archaeological site (CA-SDI-5017) required full CEQA environmental review, halting the project.
What are the main risks of mega-scale ADU projects like Chalcifica?
Mega-ADU projects face multiple compounding risks: (1) Community opposition litigation—even legally compliant projects can face CEQA challenges when environmental or cultural resources are present; (2) Financial vulnerability to stalls—carrying costs of $50,000-$75,000+ monthly continue during litigation without rental income; (3) Construction cost inflation—6-8% annual labor cost increases make original budgets obsolete during delays; (4) Legal defense expenses—CEQA litigation typically costs $150,000-$500,000+; (5) Regulatory backlash—San Diego added lot-size caps to its Bonus ADU Program in 2026, demonstrating politically vulnerable programs can change mid-project; (6) Foreclosure exposure—for a $40-60 million project, 12-18 month delays can trigger default and auction.
What is La Rinconada de Jamo and why did it halt the project?
La Rinconada de Jamo (archaeological designation CA-SDI-5017) is a Kumeyaay coastal village site with over 2,500 years of documented occupation, located at the mouth of Rose Canyon where it empties into Mission Bay. The site holds profound historical significance as the location where the first Spanish expedition in Alta California encountered a large Kumeyaay settlement on July 14, 1769. Archaeological excavations have found evidence of shellfish processing, marine mammal harvesting, and continuous occupation into the 1890s. The December 2025 court ruling determined that impacts to such a significant archaeological resource required full CEQA environmental review and discretionary permits, not the ministerial approval the city had applied.
What lessons should builders take from the Chalcifica foreclosure case?
Seven critical lessons emerge: (1) Right-size projects to neighborhood context—legal permission for 136 units doesn't mean you should build them; smaller projects (8-12 units) face dramatically lower litigation risk; (2) Conduct environmental due diligence early—commission Phase I archaeological surveys proactively rather than relying on ministerial approval to avoid CEQA; (3) Structure financing with litigation reserves—budget for 12-18 month delays, $250,000+ legal costs, and construction cost inflation; (4) Engage community before permit submission—proactive neighborhood meetings identify fatal flaws before investing in design; (5) Understand CEQA exemption limits—archaeological, tribal, and coastal resources can trigger discretionary review regardless of ADU streamlining; (6) Consult tribes early—don't wait for litigation to force the issue; (7) Base projects on stable regulatory frameworks—not maximum legal exploitation of politically vulnerable programs.
Can ADU projects still succeed in Pacific Beach after the Chalcifica case?
Yes—smaller-scale ADU projects continue succeeding in Pacific Beach with minimal opposition. Projects with 4-8 units rather than 136 units blend better with neighborhood character and face dramatically lower litigation risk. Successful developments share common characteristics: (1) Appropriate scale matching surrounding density; (2) Architectural design respecting existing neighborhood styles (craftsman, Spanish colonial, California coastal); (3) Adequate parking even though not legally required (0.5-1 space per unit); (4) Transparent community communication and willingness to adjust designs based on feedback; (5) Early environmental due diligence identifying archaeological or tribal resource concerns; (6) Phased development testing neighborhood response before full commitment. Pacific Beach's strong rental market ($2,500-$3,500+ monthly for one-bedroom units, with highest rates in blocks near the boardwalk and Crystal Pier area) still makes ADU development economically attractive—but mega-scale projects face systemic challenges beyond individual developer execution. Pacific Beach's distinctive character—combining surf culture, beach lifestyle, and proximity to UCSD—creates consistent rental demand that makes ADU investment attractive. The neighborhood's mix of long-term residents and younger renters drawn to the beach and nightlife along Garnet Avenue supports diverse ADU tenant profiles, from UCSD graduate students to young professionals to surf enthusiasts.
This article provides general information about ADU development, CEQA requirements, and foreclosure litigation in Pacific Beach for educational purposes. Laws, regulations, and project outcomes can vary by jurisdiction and specific circumstances. Always consult with qualified professionals—licensed attorneys, environmental consultants, architects, contractors, and local planning departments—and verify current City of San Diego, California Coastal Commission, and CEQA requirements before starting your ADU project. Pacific Beach Builder provides professional ADU feasibility assessments, design, permitting, and construction services throughout Pacific Beach, La Jolla, Mission Beach, and Bird Rock with expertise in coastal zone compliance and community engagement.