Midway Rising November 2026: $4.2B Project Labor Impact - Pacific Beach Builder Guide

On November 9, 2026, the San Diego City Council unanimously voted 8-0 to approve Midway Rising, a $4.2 billion mixed-use development that will transform 48.5 acres of public land in the Midway District into California's largest affordable housing project. For Pacific Beach builders, contractors, and property owners planning ADU additions or major renovations, Midway Rising represents the single largest construction labor competition event in San Diego's history.

On November 9, 2026, the San Diego City Council unanimously voted 8-0 to approve Midway Rising, a $4.2 billion mixed-use development that will transform 48.5 acres of public land in the Midway District into California's largest affordable housing project. Led by billionaire developer Stan Kroenke—owner of the Los Angeles Rams, Arsenal FC, and developer of SoFi Stadium—the project includes 4,254 housing units, a 16,000-seat entertainment arena, 130,000 square feet of retail space, and 14.5 acres of parks and public spaces.

For Pacific Beach builders, contractors, and property owners planning ADU additions or major renovations, Midway Rising represents the single largest construction labor competition event in San Diego's history. With construction crews expected to break ground at the end of 2027 and peak labor demand reaching 2,000-3,000 workers through 2030, the project will fundamentally reshape San Diego's construction labor market over the next five years.

This article provides Pacific Beach builders with actionable intelligence to prepare for the 2027-2030 labor squeeze, including construction timeline analysis, wage escalation projections, subcontractor pre-booking strategies, and geographic labor market overlap between Midway District and Pacific Beach.

Midway Rising Project Overview: What San Diego City Council Approved

After more than six hours of public comment and council deliberations, the San Diego City Council's unanimous approval on November 9, 2026 makes Midway Rising the largest affordable housing project to be built on public land in California history. The project will demolish the existing Pechanga Arena and redevelop nearly 50 acres of city-owned land.

Project Scope

  • Total Housing Units: 4,254 residential units across 18 buildings
  • Affordable Housing: 2,000 deed-restricted affordable housing units (47% of total) at an average affordability not exceeding 60% of Area Median Income, including at least 200 permanent supportive housing units
  • Market-Rate Housing: 2,254 market-rate units
  • New Arena: 16,000-seat entertainment center with an estimated cost of $520 million
  • Retail and Restaurants: 130,000 square feet of commercial space (approximately 61,000 sq ft retail and 80,000 sq ft restaurant space)
  • Parks and Public Spaces: 14.5 acres total (8.2 acres of parks and 6.4 acres of public open space)
  • Infrastructure Investment: Approximately $460 million in roads, utility, and stormwater infrastructure improvements at no upfront cost to the City
  • Total Project Value: $4.2 billion

Developer Background

Stan Kroenke brings significant real estate development experience to the project, with a net worth estimated at $27 billion as of November 2026. His previous major development—the $5.5 billion SoFi Stadium and 300-acre Hollywood Park mixed-use district in Inglewood—demonstrates his capability to execute mega-scale projects. Kroenke owns approximately 60 million square feet of real estate nationally, primarily shopping plazas, plus 2.7 million acres of ranches across the U.S. and Canada.

Financial Structure

San Diego's Independent Budget Analyst estimates the city will collect between $38.1 and $68.5 million in combined arena and development revenue over the life of the 105-year deal, not factoring in inflation. The City and Midway Rising will work with the County of San Diego to establish an Enhanced Infrastructure Financing District (EIFD), which would provide a dedicated funding source for public infrastructure and other eligible improvements.

Critics, including former San Diego City Councilmember Donna Frye, have raised concerns about the long-term lease structure and whether the city is sacrificing public interest for a private developer's vision. However, proponents emphasize the unprecedented scale of affordable housing delivery and infrastructure improvements the project provides.

Construction Timeline and Phasing: When Labor Pressure Peaks

Understanding Midway Rising's construction timeline is critical for Pacific Beach builders planning projects from 2027 through 2032. The phased approach means labor competition will intensify during specific periods, with peak demand concentrated in 2028-2030.

Construction Start

Construction crews are expected to break ground at the end of 2027, with the existing Pechanga Arena remaining open until construction is complete so sports events and concerts won't be disrupted.

Phase 1 (2027-2030)

  • Demolition of the site east of proposed Frontier Drive
  • Construction of the new 16,000-seat Entertainment Center while the existing arena remains operational
  • Construction of approximately 91,000 sq ft of commercial space (40,000 sq ft retail and 52,000 sq ft restaurant)
  • Construction of residential and commercial uses east of Frontier Drive
  • Construction of Frontier Drive
  • Anticipated Completion: 2030

Phase 2 (2030-2035)

  • Demolition of the existing arena (once the new Entertainment Center is operational)
  • Construction of approximately 49,000 sq ft of commercial space (21,000 sq ft retail and 28,000 sq ft restaurant)
  • Construction of commercial and residential uses west of Frontier Drive
  • Anticipated Completion: 2035

Overall Duration

The full development is expected to be completed over 10 to 20 years, though the most intensive construction activity will occur during Phase 1 (2027-2030).

Peak Labor Demand Analysis

At peak construction, Midway Rising is estimated to employ 2,000-3,000 construction workers simultaneously. This represents approximately 2.3-3.4% of San Diego County's entire construction workforce, which currently numbers around 87,000 workers. When combined with other major projects—SDSU Mission Valley (3,500-5,550 workers), Riverwalk San Diego at Fashion Valley (4,300 homes), and ongoing San Diego Airport Terminal 1 Phase 1B construction—the region faces unprecedented labor demand.

Critical Window for Pacific Beach Builders

The 2028-2030 period represents the highest risk for Pacific Beach contractors. During these years, Phase 1 residential construction will be in full swing, requiring large crews of framers, electricians, plumbers, and concrete workers—the same trades essential for Pacific Beach ADU construction and major renovations.

Geographic Labor Market Overlap: Why Midway Rising Directly Impacts Pacific Beach

Pacific Beach and the Midway District share the same construction labor pool, making Midway Rising a direct competitive threat for Pacific Beach contractors seeking qualified crews.

Distance and Commute Patterns

The Midway District is located at the northern end of the Point Loma peninsula, northwest of downtown San Diego, and just west of Old Town. Pacific Beach sits approximately 8-9 miles north of the Midway District—a commute of 15-25 minutes depending on traffic. Research shows that 99% of San Diego residents can commute almost anywhere in San Diego County within an hour, suggesting that construction workers could readily serve projects in both locations.

Integrated Regional Labor Market

San Diego's construction labor market operates as an integrated regional system. Union workers follow radius rules established between the local union hall and the worksite, while non-union contractors draw from overlapping networks of independent tradespeople who work throughout the county. With San Diego County operating at a 12% construction labor vacancy rate—well above the healthy 7-8% benchmark—any large project can tip the balance and create widespread shortages.

Specialized Coastal Expertise

Pacific Beach projects require specialized coastal construction expertise, including foundation engineering for sandy soils, corrosion-resistant materials for saltwater environments, and familiarity with California Coastal Commission permitting requirements. This specialization means the pool of qualified contractors for Pacific Beach is significantly smaller than for general San Diego construction. When general contractors working on Midway Rising need to poach specialized crews to meet their schedules, Pacific Beach's coastal specialists become prime targets for higher-paying opportunities.

Wage Competition Dynamics

Mega-projects like Midway Rising can afford to pay premium wages to attract and retain labor. Stan Kroenke's SoFi Stadium project in Inglewood, for example, was known for offering above-market rates to ensure schedule adherence. If Midway Rising follows a similar strategy, Pacific Beach contractors may find themselves needing to increase wages by 10-15% above already elevated 2026 rates just to retain existing crews.

Construction Labor Shortage Context: San Diego's Pre-Existing Crisis

Even before Midway Rising's approval, San Diego faced a severe construction labor shortage that was driving up costs and extending project timelines. The addition of 4,254 housing units to an already stressed system will intensify these challenges.

Current Vacancy Rates

San Diego's construction industry faces a critical 12% vacancy rate as of May 2026, driving project delays and cost increases for Pacific Beach ADU and coastal builds. This compares unfavorably to the healthy benchmark of 7-8%. A survey found that 94% of contractors struggle to fill openings, with labor shortages directly impacting 52.1% of projects and adding an average of 5.5 months to schedules.

Regional Worker Deficit

San Diego needs to build approximately 108,000 new housing units by 2029 to meet state requirements. That translates to roughly 12,000 additional residential construction workers needed annually—a 22% increase from current levels of approximately 87,000 workers. Even without Midway Rising, the region faces a substantial workforce gap.

Wage Escalation Trends

Wages are rising 6-8% annually across skilled trades, with San Diego construction workers earning a median of $67,580—approximately 20.4% above the national median. San Diego labor costs run approximately 23% above the national average across all construction trades, with skilled trades commanding even higher premiums.

Current 2026 Hourly Wage Ranges by Trade

Trade Experience Level Hourly Rate Range Prevailing Wage (Public Projects)
Framer General $23.59/hr Not specified
Electrician Helper/Apprentice $19-$30/hr $78.09/hr (Inside Wireman)
Electrician Journeyman $61-$77/hr $78.09/hr
Electrician Master $78-$89/hr $78.09/hr
Plumber Helper/Apprentice $16-$27/hr $90.19/hr (General/Industrial)
Plumber Journeyman $52-$67/hr $90.19/hr
Plumber Master $68-$78/hr $90.19/hr

Projected Wage Increases 2027-2030

If current 6-8% annual wage increases continue through 2027-2030, Pacific Beach builders can expect:

  • 2027: Journeyman electrician rates of $65-$83/hr (6-8% increase)
  • 2028: Journeyman electrician rates of $69-$90/hr (cumulative 13-17% increase)
  • 2029: Journeyman electrician rates of $73-$97/hr (cumulative 20-26% increase)
  • 2030: Journeyman electrician rates of $77-$105/hr (cumulative 26-36% increase)

These projections assume baseline wage growth. If Midway Rising triggers a bidding war for skilled labor during peak construction years (2028-2030), actual increases could be significantly higher.

Comparison to Other San Diego Mega-Projects

To understand Midway Rising's unprecedented labor impact, it's helpful to compare it to other major San Diego construction projects.

SDSU Mission Valley

SDSU Mission Valley includes approximately 4,600 residential units for students, faculty, staff, and the public, plus roughly 1.6 million square feet of office, technology, and research space. Clark Construction employed an estimated 3,500 to 5,550 workers through both the stadium and site development phases. SDSU Mission Valley is projected to expand the university's economic impact in the region by $3 billion annually.

Riverwalk San Diego (Fashion Valley Area)

At Riverwalk San Diego off Friars and Fashion Valley roads, the existing golf course will be turned into 4,300 homes on 200 acres. This project, combined with SDSU Mission Valley and Midway Rising, accounts for roughly 13,000 planned homes in San Diego County.

San Diego Airport Terminal 1 Phase 1B

The $3.8 billion airport terminal project impacts Pacific Beach construction labor and subcontracting availability. The airport's $14.44 million roadway project alone creates labor competition for Pacific Beach, La Jolla, Mission Beach, and Bird Rock contractors through fall 2027.

Measure HH College Construction

The San Diego Community College District launched more than a dozen major construction projects worth over $1.3 billion in 2026, creating immediate opportunities and competition for Pacific Beach contractors through 2028.

Combined Impact

Together, these projects demonstrate that Midway Rising is not an isolated labor demand event—it's one component of an unprecedented regional construction boom. The cumulative effect is a perfect storm of labor scarcity that will force Pacific Beach builders to compete aggressively for available crews.

Scale Comparison

Midway Rising's 4,254 housing units represent approximately 10 times the size of a typical large Pacific Beach residential project. For context, the average Pacific Beach ADU project involves 1-2 units, while even substantial Pacific Beach multifamily developments rarely exceed 50-100 units. The sheer scale of Midway Rising means it can absorb entire subcontracting companies' capacity for months or years at a time.

Six-Step Action Plan for Pacific Beach Builders: Preparing for the Labor Squeeze

Pacific Beach builders and property owners must act now—before construction begins in late 2027—to secure labor for projects planned through 2030. Here's a comprehensive action plan:

Step 1: Pre-Book Subcontractors 6-12 Months Ahead

Key trades should be locked in early—for example, calling an electrical contractor during the pursuit phase rather than waiting until the guaranteed maximum price (GMP) stage, to get them committed before competing projects do. Subcontractor crew availability should be confirmed in writing, not just verbal assurances from months prior.

For Pacific Beach projects starting in 2028-2030 (the peak Midway Rising construction years), begin conversations with subcontractors by mid-2027. Request written commitments with specific crew allocation and start date windows.

Step 2: Build Wage Escalation Clauses Into Contracts

With 6-8% annual wage increases expected to persist through 2027, and potentially accelerate to 10-15% during peak Midway competition, project budgets must include wage escalation clauses. For projects spanning multiple quarters, include language allowing for adjustment based on documented market rate increases.

Consider structuring contracts with quarterly wage review periods, indexed to Bureau of Labor Statistics data for San Diego construction wages or local union wage scales.

Step 3: Expand Your Crew Network Beyond San Diego County

Comparisons between San Diego and Los Angeles construction labor markets show that contractors willing to recruit from neighboring counties can tap into less constrained labor pools. While this introduces coordination challenges and potential travel time costs, it may be essential during peak shortage periods.

For specialized coastal work, consider reaching out to contractors in Orange County (Huntington Beach, Newport Beach) who have similar saltwater environment experience. For general framing and foundation work, Riverside and Imperial County contractors may provide backup capacity.

Step 4: Invest in Modular and Prefabrication Solutions

San Diego's construction sector is adopting prefabrication and modular construction faster than Los Angeles, reducing on-site labor needs by approximately 15-20% for comparable projects. San Diego leads California's modular housing revolution with 2,000 factory-built units in 2026.

For ADU projects in particular, modular construction can reduce on-site labor requirements by up to 80%, with most work completed in controlled factory environments. While modular solutions require different permitting approaches and design considerations, they offer a viable strategy to bypass labor competition entirely.

Governor Newsom's 2026 modular construction push includes legislation requiring that modular housing receiving state incentives be manufactured in California factories, ensuring long-term supply chain development.

Step 5: Add 10-15% Schedule Buffer for Labor Delays

Project schedules should include a 10-15% labor float to account for potential delays. For a typical 6-month Pacific Beach ADU project, this translates to 3-4 weeks of buffer time. For larger 12-month renovations, plan for 6-7 weeks of potential labor-related delays.

Communicate realistic timelines to clients upfront. Property owners who understand the labor market constraints will be more patient with schedule adjustments and less likely to demand penalty clauses that contractors cannot reliably avoid.

Step 6: Prioritize Projects with Flexible Timelines

From 2028-2030, consider prioritizing clients who have flexibility in project start dates and can adjust schedules if crew availability shifts. Projects with hard deadlines (such as those tied to lease expirations or property sales) will require premium pricing to justify the risk of needing to hire more expensive spot labor.

Create a tiered pricing structure: standard pricing for projects with 2-3 month schedule flexibility, premium pricing (10-15% higher) for firm timeline projects, and rush pricing (25-35% higher) for expedited work during peak competition periods.

Coastal Development Permit Timeline Considerations

Pacific Beach's location within the California Coastal Commission's Coastal Overlay Zone adds another layer of complexity to construction planning during the Midway Rising era.

Current Permit Timelines

As of May 2026, San Diego Development Services permit issuance queue times average 1 business day for standard building permits and 4 days for demolition, mechanical, plumbing, and electrical permits. However, most Pacific Beach projects fall within the coastal zone, requiring additional Coastal Development Permits that extend timelines to 6-12 months.

AB 462 Improvements for ADUs

AB 462's 60-day coastal ADU permit timeline represents a significant regulatory improvement for smaller projects, cutting approval periods from 6-18 months to two months. This creates a strategic advantage for ADU projects over larger multifamily developments that don't qualify for the expedited process.

Budget Crisis Impact

A critical concern for the second half of 2026 and beyond: Independent Budget Analyst Charles Modica warns of a $110 million budget deficit forcing Development Services cuts and permit delays starting July 1, 2026. ADU permits in Pacific Beach will likely face 2-3 month additional delays for non-coastal projects and 2-4 month delays for coastal zone ADUs requiring Coastal Development Permits.

Strategic Implications

Property owners planning Pacific Beach construction projects for 2028-2030 should initiate permit applications by mid-2027 at the latest. This allows for 6-12 months of coastal permitting, plus 2-4 months of budget-crisis-related delays, to secure approvals before desired construction start dates.

Consider front-loading permitting costs and professional fees in 2026-2027, before wage inflation and labor competition drive up all project costs in 2028-2030.

Long-Term Market Implications: Post-Midway Rising Opportunities

While Midway Rising creates short-term labor challenges for Pacific Beach builders, it also signals long-term opportunities.

Skilled Labor Development

Mega-projects typically provide training and skill development opportunities that expand the overall labor pool. Workers who gain experience on Midway Rising will enter the market with enhanced skills in large-scale project management, advanced construction techniques, and potentially BIM (Building Information Modeling) capabilities that command 30-45% higher wages.

By 2032-2035, as Midway Rising completes Phase 1 and transitions to Phase 2, Pacific Beach builders may find a larger, more skilled labor pool available than existed in 2026.

Modular Construction Infrastructure

The push toward modular construction to address labor shortages will result in expanded factory capacity and supply chains in California. San Diego's 2,000 factory-built units in 2026 represent just the beginning of a structural shift toward industrialized construction methods that could benefit Pacific Beach builders long-term.

Wage Stabilization

While wages will increase significantly from 2027-2030, the completion of multiple mega-projects (Midway Rising, SDSU Mission Valley, Riverwalk San Diego) around 2030-2032 should reduce competitive pressure and potentially stabilize or even decrease wage growth rates. Builders who maintain relationships with quality crews through the shortage years will be positioned to benefit from more favorable conditions in the early 2030s.

Market Repositioning

Some Pacific Beach contractors may find opportunities to work as subcontractors on Midway Rising itself, gaining access to steady work at premium rates. While this reduces capacity for independent Pacific Beach projects, it provides financial stability and experience that can be leveraged for larger future projects.

Frequently Asked Questions

When will Midway Rising construction actually start affecting Pacific Beach labor availability?

Construction crews are expected to break ground at the end of 2027, but the most significant labor pressure will occur during Phase 1 (2027-2030), with peak competition in 2028-2030 when residential construction is in full swing. Pacific Beach builders should begin pre-booking subcontractors by mid-2027 for any projects planned in the 2028-2030 window. The impact will be felt earlier than actual construction starts, as general contractors for Midway Rising will begin securing subcontractor commitments 6-12 months before breaking ground.

How much more expensive will Pacific Beach construction projects become due to Midway Rising?

Baseline wage growth of 6-8% annually is already projected through 2027. During peak Midway Rising construction years (2028-2030), labor costs could increase an additional 10-15% above baseline due to competitive bidding for scarce crews. For a typical $400,000 Pacific Beach ADU project where labor represents 40-50% of costs ($160,000-$200,000), this translates to potential cost increases of $16,000-$30,000 beyond normal inflation. Projects requiring specialized coastal construction expertise may face even higher premiums as general contractors working on Midway Rising attempt to poach these specialized crews.

Should Pacific Beach property owners delay construction projects until after Midway Rising is complete?

This depends on individual circumstances, but generally, delaying may not save money. While labor costs will be higher during 2028-2030, waiting until Phase 1 completion (2030) means missing 2-4 years of potential rental income from ADUs or property appreciation from improvements. For an ADU generating $3,000/month in rental income, delaying from 2028 to 2030 means forgoing approximately $72,000 in gross rental income. Additionally, construction costs have increased 44% since 2021 and show no signs of long-term decrease. The best strategy is to build when you need the space or income, with realistic budgeting for current market conditions. For non-urgent projects, targeting construction starts in 2027 (before peak competition) or 2031-2032 (after Phase 1 is substantially complete) may offer more favorable labor conditions.

Will Midway Rising affect construction permit timelines in Pacific Beach?

Midway Rising itself should not directly impact Pacific Beach coastal development permit timelines, as these are processed through separate regulatory channels (California Coastal Commission vs. city planning approvals). However, the broader construction boom and San Diego's $110 million budget deficit may cause staffing shortages at Development Services, adding 2-4 months to permit processing times. The good news is that AB 462's 60-day coastal ADU permit timeline provides a fast-track option for ADU projects that can help bypass some delays. Property owners should initiate permit applications 6-12 months before desired construction starts to account for coastal permitting requirements plus potential budget-related delays.

How does Midway Rising compare to other San Diego mega-projects in terms of labor competition?

Midway Rising's 4,254 housing units make it larger than most individual San Diego projects, but it's part of a broader construction boom. SDSU Mission Valley employed 3,500-5,550 workers and includes 4,600 residential units. Riverwalk San Diego will add 4,300 homes. The San Diego Airport Terminal 1 Phase 1B ($3.8 billion) and Measure HH college construction projects ($1.3 billion) add to regional demand. Together, these projects account for roughly 13,000 planned homes and require an estimated 12,000 additional construction workers—a 22% increase from current levels. Midway Rising is the single largest project, but the cumulative effect of all concurrent mega-projects creates the labor shortage, not Midway Rising alone.

Can Pacific Beach builders work as subcontractors on Midway Rising to gain access to steady work?

Yes, this represents a viable strategic option for some contractors. Stan Kroenke's development team will need to hire numerous subcontractors across all trades for the 10-20 year project duration. Pacific Beach contractors with expertise in multifamily residential construction, particularly those with experience in large-scale projects, may find opportunities to bid on specific building packages within the development. However, working on Midway Rising will reduce capacity for independent Pacific Beach projects. Contractors should evaluate whether they prefer the stability and scale of mega-project work versus the flexibility and potentially higher margins of custom coastal construction. Some firms may adopt a hybrid approach, allocating one crew to Midway Rising for steady income while maintaining another crew for Pacific Beach specialty work.

What trades will be most impacted by Midway Rising labor competition?

The most severely impacted trades will be those required in high volumes for both multifamily residential construction and Pacific Beach ADU/renovation work: framers, electricians, plumbers, concrete workers, and drywall installers. Currently, journeyman electricians earn $61-$77/hr and journeyman plumbers earn $52-$67/hr. These trades will see the most intense bidding competition during 2028-2030. Specialized trades like HVAC technicians, solar installers, and roofing crews will also face increased demand. Ironically, some highly specialized coastal construction trades (marine engineering, specialized foundation work for sandy soils) may be less impacted because Midway Rising's inland location doesn't require coastal expertise, limiting the ability of Midway contractors to poach these specialists.

Is modular construction a realistic option for Pacific Beach projects during the labor shortage?

Yes, modular construction is increasingly viable and can reduce on-site labor needs by 15-20% for standard projects, with some applications achieving up to 80% reduction by moving work to factory environments. San Diego leads California with 2,000 factory-built units in 2026, and Governor Newsom's 2026 legislation is accelerating modular adoption. For Pacific Beach ADU projects, modular solutions can bypass much of the labor competition while potentially offering faster construction timelines. However, modular construction requires different design approaches, may face some regulatory challenges in coastal zones, and typically requires larger upfront deposits. Property owners should consult with contractors experienced in both traditional and modular construction to evaluate whether modular is appropriate for their specific project. Modular is most cost-effective for ADUs and smaller residential projects; custom luxury renovations may not benefit as much from factory-built approaches.

Will wages decrease after Midway Rising is complete?

Unlikely to see significant decreases, but wage growth rates should moderate. Construction wages rarely decrease in absolute terms; instead, periods of high inflation are followed by periods of slower growth. After Phase 1 completion around 2030 and as multiple mega-projects wrap up (SDSU Mission Valley, Riverwalk San Diego), competitive pressure should ease, potentially reducing annual wage growth from 6-8% to 3-4%—closer to general inflation rates. Workers who gain skills and experience on mega-projects also increase their productivity and value, justifying sustained higher wages. By 2032-2035, Pacific Beach builders should find a larger, more skilled labor pool, but at permanently elevated wage levels compared to 2026. The key is that wage growth rates moderate, not that wages themselves decrease.

What should Pacific Beach property owners do right now if they're planning a 2028-2029 construction project?

Take these five immediate actions: (1) Start conversations with contractors now to get preliminary bids and understand current lead times—contractors with existing relationships will prioritize repeat clients during shortages. (2) Initiate coastal development permit applications if your project is in the coastal zone, allowing 6-12 months for processing. (3) Increase your construction budget by 15-25% above current estimates to account for 2028-2029 labor cost increases. (4) Ask contractors specifically about their strategies for securing crews during the Midway Rising peak years—contractors with solid plans (pre-booked subs, modular options, out-of-county labor sources) are more likely to deliver on time and budget. (5) Consider whether accelerating your project to 2027 or delaying to 2030-2031 makes financial sense based on your specific needs and the trade-off between labor costs and lost time/income. The worst strategy is to wait until 2028 and hope for the best—labor markets don't improve spontaneously during mega-project construction phases.